Create one work order for a single manufactured SKU without grouping it in a production run, or add it to an existing run later.

Collection: Work Orders: Getting Started
Priority: P1


Who this is for

Production planners who need a one-off manufacturing job rather than a full production run batch.

Before you begin

Steps

1. Open the create form

Go to Inventory → Work Orders → Orders, then click Create Work Order.

2. Product Information

FieldNotes
Co-ManufacturerManufacturing vendor
Select SKUFinished good to produce
Bill of MaterialsAuto-populated from the SKU; confirm or override
Planned QuantityUnits to manufacture
UnitSelling/stockkeeping unit

3. Logistics

FieldNotes
Production LocationWhere manufacturing occurs
Destination WarehouseWhere finished goods go
Service Fee (per unit)Manufacturing service fee; may auto-resolve from cost rules

4. Schedule & Completion

FieldNotes
Expected Completion DateTarget finish date
Production RunOptional — link to an existing run
Completion TriggerFinish Step (standard batch + assembly flow) or Receipt (subcontract receive-at-destination)

For co-man batch production, use Finish Step.

5. Additional Information

Add Notes, Alternate IDs, and any Custom Fields as needed.

6. Review BOM supply methods

The inline BOM table shows each component's Supply Method (On Hand, Purchase Order, etc.). Adjust per line if needed.

7. Save

Click Create (or Save). The work order opens in Draft status.

What happens next

From the work order detail page:

  • Review the Bill of Materials tab for shortages
  • Use Generate Purchase Orders, Plan, Start, and Quick Complete as described in the run-based guides
  • Optionally link the work order to a production run from Edit → Production Run

Still stuck?

Contact support if the SKU or BOM does not appear when selected.