How Cost Layer Rebuilds Cascade to Assembled Products

When Luminous runs a cost-layer rebuild (nightly or on-demand), it recalculates the landed cost of your raw components and purchased SKUs based on your receiving reports and associated freight, duty, and handling charges.

If a component's cost changes during that rebuild, Luminous now automatically propagates the correction to any assembled finished goods that:

  1. Consumed that component through a completed assembly order, and
  2. Still have on-hand inventory remaining in the warehouse.

This means your assembled product's inventory value and cost-per-unit will reflect the updated component cost without any manual intervention.

Note: This cascade is being rolled out tenant-by-tenant and is not yet automatic for every account. If you don't see assembled-product costs updating after a rebuild even though a component cost changed, confirm with Luminous support that this behavior has been enabled for your account. Separately, the nightly cost-layer rebuild itself is opt-in — check with support that it's turned on for your account before expecting rebuilds to run without being triggered manually.

What gets updated — and what does not

ScenarioBehaviour
Finished goods still on hand after the rebuildCost layer re-valued to reflect the corrected component cost
Finished goods fully sold or consumed before the rebuild runsNot updated (no remaining quantity to restate)
Finished goods assembled from other assembled goods (nested assemblies)Cascade runs in multiple passes — up to 8 levels deep
Layers dated inside your closed accounting periodSkipped — the closed period is never modified
Layers with a manual cost override applied by a userNot affected by the cascade; manual overrides are preserved

Why the cost might still look unchanged after a rebuild

If your assembled product's cost did not update after a rebuild, check these common reasons:

  • All finished-good inventory has been sold. If there is no remaining on-hand quantity in the warehouse, there is nothing to restate.
  • The component cost did not actually change during the rebuild. The cascade only fires when a component's per-unit cost moves. If the rebuild determined the existing cost was already correct, no cascade is triggered.
  • The assembly order's finished-good layer falls inside a closed accounting period. Layers created on or before the period-close date are intentionally skipped.
  • A manual cost override is on the finished-good layer. Manual overrides are preserved and are not altered by rebuilds.

How this interacts with the nightly rebuild

The cascade runs automatically at the end of every cost-layer rebuild — both the nightly scheduled run and any on-demand rebuild you trigger from the Cost Layer Repair tools. No additional steps are needed.

Tip: If you want to preview what a rebuild would change before committing, use the dry-run mode available in the Cost Layer Repair API. The dry-run output shows which assembly-order tranches would be restated and by how much.